We’ve recently completed construction of a water well to supply a popular car wash facility in the Swindon area.
Working closely with the main contractor, our careful pre-planning enabled us to install a 40m deep water well in challenging geological conditions, requiring 25m of retrievable casing to be used, all without affecting the site’s redevelopment programme.
On-going site contamination issues dictated that the borehole construction had to be professionally approved and tested before use. But the results of the post-development pump testing confirmed the well would supply a clean water yield in excess of the client’s requirements.
The savings in water supply costs for our client equates to a significant increase in their future profits. What difference would a free supply of 20,000 litres of water a day make to your business?
Contact: Angus Gale Tel: 01296 739471