Ok, that claim may be stretching things a little, but our forensic analysis team have recently notched up a few notable successes. We were awarded a contract to treat petrol and diesel contamination in the soil and groundwater under a filling station. The site had a history of leaks, the most recent of which was six years ago. Since then one of our competitors had been trying (and failing) to clean the site up.

We were brought in to deal with the contamination once and for all. The first thing we did was to carry out some forensic analysis of the contamination using proprietary methods we have developed over the last 20 years. Our analysis indicated that there was an ongoing leak at the site, and was even able to pinpoint where on the site it was likely to be.

Our client commissioned precision tank and line testing which confirmed a slow leak under pump island 7 – just where we had predicted. The rate of leak – 0.29litres/hour – was actually below the precision testing threshold, meaning that the fuel lines passed the test and were certified as ‘not leaking’. However, this rate of leak would result in around 2,500litres of fuel entering the ground under the site each year – more than enough to cause serious contamination.

So the lessons learnt? Firstly, tank and line testing is very far from foolproof and fails to identify leaks that can cause serious environmental issues. Secondly, the timely use of forensic analysis can prevent significant time and money being wasted on ineffective remediation work.

For further information on our forensic analysis capabilities please contact Duncan Eastland or Kate Clark.

Big Old Tanks

USTsHave you ever wondered what is below your feet when you’re filling up at a petrol station? Big old tanks, that’s what! We’ve investigated the ground at more filling stations in the UK than anyone else and so, not surprisingly, we have a have a pretty detailed understanding of how they are put together. This sort of experience is invaluable when
it comes to assessing potential environmental risk – we know how and where problems
can occur…

Obviously owning our own specialist drilling systems, UKAS and MCerts accedited
laboratory and remediation equipment also has benefits, both in terms of cost and speed of turnaround.

For pragmatic advice and cost effective assessment strategies for the assessment
of filling station sites please contact James Skinner on 07770 611554.

Free Water Supply?

Water Well Drilling
Water Well Drilling

We’ve recently completed construction  of a water well to supply a popular car wash facility in the Swindon area.

Working closely with the main contractor, our careful pre-planning enabled us to install a 40m deep water well in challenging geological conditions, requiring 25m of retrievable casing to be used, all without affecting the site’s redevelopment programme.

On-going site contamination issues dictated that the borehole construction had to be professionally approved and tested before use. But the results of the post-development pump testing confirmed the well would supply a clean water yield in excess of the client’s requirements.

The savings in water supply costs for our client equates to a significant increase in their future profits. What difference would a free supply of 20,000 litres of water a day make to your business?

Contact: Angus Gale Tel: 01296 739471

When Things Get Tricky

Removing USTs with truss in foreground

Subadra have recently completed what has been, perhaps, our trickiest ever underground tank removal. The tanks at the former filling station were located close to the site boundary. Removing them might destabilise a Victorian house on the adjacent property. To prevent this a contiguous bored pile wall was installed together with a supporting steel truss. Our job was to safely ease the tanks out from under the truss without compromising its structural integrity, before cutting them up and disposing of them as scrap metal. All this on a crowded site with construction of the new structures well underway.

Contract Value £20-£50k

Property Portfolio Due Diligence

Subadra has just completed environmental investigations at a portfolio of 25 retail petrol filling station sites on behalf of a major oil company. The project was brought to completion on time and on budget, using a combination of our own drilling equipment, our in-house UKAS accredited laboratory and reported by our highly experienced consultants.

Contract Value: £100-200k

When Wetstock Monitoring Doesn’t Work

It has become increasingly common in recent years for filling station operators to rely on remote wetstock monitoring to detect possible leaks in their system. Tank and pump gauges are monitored remotely with sophisticated trend analysis used to detect abnormal behaviour. These systems can be very good, but they aren’t infallible.

Last year Subadra were retained to clean up contamination resulting from a leak at a filling station. Our treatment was completed successfully over the winter months and by mid-summer we had started post-remedial monitoring, with groundwater samples taken at monthly intervals from monitoring wells we had installed at the site.

Our consultants noticed some anomalous results appearing and, in best CSI fashion, our laboratory carried out a programme of forensic analysis. This was able to determine the ‘age’ of the contamination we were finding, telling us how long the leaked fuel had been in the ground. This confirmed that the wells were being contaminated from a new source.

The site’s real-time remote wetstock monitoring was checked but didn’t show a leak at the site. However, on our advice, the site operator had the tanks and lines pressure tested and this identified a steady slow leak from one of the pumps. Repairs were carried out limiting the volume of fuel lost into the ground.

The moral of the tale? Well, remote wetstiock monitoring is very good and we would certainly recommend it. But it’s not infallible. In those cases, forensic analysis can help identify leaks that wetstock monitoing misses.

If you’d like to know more about our forensic analysis service or any of the other services offered by our UKAS/MCerts accredited laboratory please contact Kate Clark.

Tight Deadlines?

Tight Acquisition Deadline?

Sometimes you need a detailed ground investigation with large numbers of boreholes, utilising a variety of different investigation tools (drill rigs, plate bearing tests, pile probing etc), with data collected and assimilated over a period of days or even weeks, that delivers a detailed description of site geology and provides a well defined contaminant delineation.We can do this for you.

However, sometimes you need a basic no frills contamination survey that is both cost effective and done on a very fast turnaround.Here at Subadra we own and operate our own survey team, drill rigs, chemical analysis laboratory in addition to our team of highly skilled geotechnical and environmental consultants that are responsible for collating, assessing and the reporting the data we produce. This means we can carry out high quality, cost effective Phase One and Two contamination surveys within days.This service proves invaluable for may of out clients who are always on the lookout to purchase new sites to add to their portfolio and don’t want to lose out on a lucrative deal or, perhaps worse, get caught out by discovering contamination issues after the site has been purchased.

We recently carried out a survey at a filling station site in Hampshire that was instructed on a Friday at 4pm and we had carried out a below ground utilities survey, borehole investigation, groundwater monitoring and sampling, all analysis and data reported to the client by the following Thursday. Now how does that compare with the service you currently receive from your consultant?
Contract value: £4.5k

Subadra Awarded Multi-Site Portfolio

We have been awarded the contract to carry out pre-redevelopment site investigations at a portfolio of approximately 30 filling stations across the UK for a major fuel retailer. The contract requires both environmental and geotechnical assessment of each site. Key to our successful bid was the fact that we will be carrying out all the work using our own drilling rigs and our own UKAS/MCerts laboratory, allowing us to be confident of meeting the very demanding project deadlines. This contract confirms our position as the UK’s #1 environmental consultancy in the retail fuel sector.

Water, Water Everywhere

Treatment System in Operation

We are currently assisting in the treatment of construction wastewater from a filling station redevelopment in Dorset. Working with the primary works contractor, we provided a system that is capable of pumping and treating high volumes of hydrocarbon-contaminated water from deep excavations.

Our in house designed, modular treatment plant was efficiently dealt with two both suspended solids and hydrocarbon contamination, ensuring all the effluent met the site’s discharge licence conditions.

We installed and tested the system at an early stage of the works allowing us to collect and analyse samples in our UKAS accredited laboratory and use this information to assist in obtaining a temporary discharge license from the local sewerage undertaker. This meant the
contractor was able to discharge effluent direct to the foul sewer.

With the high costs and project delays associated with tankering hydrocarbon-contaminated wastewater from site our fully mobile and modular dewatering systems are a simple and cost effective way of dealing with dewatering effluent.

Project value: less than £10k

Motorway Service Area Investigation

Earlier this month we were awarded a contract to investigate the forecourt area at a motorway service area in southern England, for a major oil company, as part of a leasehold transition.
With data from over thirty boreholes and monitoring wells this was a relatively detailed investigation for forecourt investigation. However, our client understood that carrying our a comprehensive combined environmental and geotechnical ground investigation at an early stage invariable pays saves money in the long run.
We used our GeoProbe direct-push drilling system to construct boreholes, targeting key areas such as the below-ground fuel tanks, fuel lines and forecourt interceptor. We then analysed the soil and groundwater samples for our hydrocarbon suite at our own UKAS
accredited laboratory.
Our investigation report has provided our client with a detailed baseline study confirming ground quality and highlighting any areas of contamination at the time they took over mangement of the site.
Contract value £25k