Sadly not in this case. But what do you do if you’re digging a hole and it fills with a horrible mixture of black fuel and water? Call Subadra of course! We are able to guide you with all aspects of contaminated ground from waste disposal or how to minimise the impact on your development programme to how to discharge your planning conditions.
The site in the photo is a filling station that is currently undergoing a full site redevelopment. When the contractor opened up the forecourt to remove the below ground fuel tanks the excavation filled with a heady mix of petrol and diesel that had accumulated over the years around the off-set fill points.
We were on-site within 2hours of being contacted. We collected water and soil samples from the excavation that were run through our in-house hydrocarbon laboratory. The results were issued within 48hours allowing the contractor to efficiently deal with the soil disposal and avoid costly delays to the works programme.
Subadra Appointed to Advise Retail Motor Industry Federation
Subadra have been appointed by the Retail Motor Industry Federation (RMI) to provide specialist environmental advice to their members. The RMI represents the interests of petrol retailers and forecourt operators across the UK. They provide support on matters ranging from contaminated fuel problems to getting a better deal with your fuel supplier.
We join their technical support team in providing practical and sensible advise for all matters associated with fuel leaks, spills and ground contamination issues.
Whether you need guiding through the planning process during a site redevelopment or you suspect you may have had a fuel leak – we can help.
Please contact James Edley(Tel. 01296 739412 or email) for further information.
Subadra win multi-site forecourt investigation package
Subadra have recently been awarded a package of investigation works by one of the major oil companies. We were selected based upon our continued excellent working relationships with the end client and their project managers , continuing to provide a high quality service and as always being able to offer cost effective site investigation services.
Particular praise was made of the quality of our tender submission, highlighting key areas of excellence and capabilities which enabled the client to quickly and easily conclude that we were the service provider best suited to complete the works.
The works package includes investigating 12 retail filling sites using our GeoProbe direct-push drilling system. The majority of the chemical analysis will be completed by our UKAS accredited laboratory. The reporting deadlines for the package is six weeks from the point of instruction. Contact value: ~£55k+
There are always cost savings to be made when multi-site packages are being completed and we like to pass these savings onto the client. If you have a small network of filling station sites or are a ‘Top-50’ operator and need an environmental survey get in touch to discuss our highly competitive rates.
Subadra Complete New Fuel Storage Facility For Millenium Seedbank
This month saw us complete construction of a new fuel storage facility for Royal Botanic Gardens’ Millenium Seed Bank. A key aspect of the project was to ensure that the Seed bank was continuously supplied with fuel (used for heating greenhouses) as any protracted outage would have had dire consequences for the seeds. In the event the switchover was completed without a hitch.
Subadra were responsible for all the civils works (constructing the tank base and retaining walls, installing a dedicated drainage and spill capture system, electrical installation etc. Our partner, Vectec, were responsible for supplying and installing the tanks and associated pipework.
Contract Value: £50-100k